Enterprise transformation 2 min read

A 23-project program, accepted into operations

At a glance

The challenge

Connect 23 projects so a completed component did not leave the next team blocked.

My responsibility

I led eight direct-report PMs and owned dependencies, integration, acceptance and handover.

The decision

Completion required working technology, usable handoffs and independent local operation.

Program outcome

The agreed scope was completed within the approved $32M budget and three-year timetable.

Context
Energy company · Enterprise transformation
Period
Three-year program delivery
Jump to program outcomes

Context

How the work connected.

Background and context

My responsibility was making the projects work together—and ensuring local teams could operate the result independently. Reporting to the CDO, I owned sequence, dependencies, integration, acceptance and handover across 23 projects, 25 teams and 15 vendors.

Separate applications could meet their milestones while leaving the next team blocked. Changed geological assumptions could invalidate a plan; a finished schedule could still lack the inputs Drilling needed.

The decision, illustrated

Completion mattered at the handoffs.

Geology layers, a business-case sheet, a planning board, a drilling rig and an accepted operating view stand on one shared foundation. A blue bridge and acceptance checkpoint highlight the planning-to-drilling handoff.
Five connected stages
Geology, business case, planning, well construction and operation depended on shared data and usable handoffs.
Planning to drilling
Work sequence, materials and readiness had to align before the next team could proceed.
Receiving readiness
I kept acceptance open until the handoffs and local operating process worked.

An illustration of cross-project dependencies and acceptance, not a physical system architecture or a count of applications.

total approved program budget
$32M
approved delivery timetable
3 years
direct reports
8 PMs

Judgment

The decisions between the projects.

The central trade-off

Technical closure could protect a reporting milestone while leaving Operations dependent on project support. I kept acceptance open and used the approved reserve to complete process and handover work.

  1. 01

    Correct the milestone, not just the status.

    Planning reported a completed schedule, but Drilling still lacked the work sequence and materials information. I had defined receiving-team acceptance too late. I brought both PMs together, agreed the missing inputs and separated a draft plan from an execution-ready handoff.

  2. 02

    Resolve the exchange without rebuilding every system.

    Two vendors used incompatible well-data references and formats. With the data owner and vendor leads, I approved limited interface changes plus integration mapping over full standardization. Engineers implemented the fix. Acceptance required correct received records and a complete business scenario. I deferred a reporting enhancement to release specialists and protect program milestones.

  3. 03

    Keep responsibility open until operations can take over.

    Technical tests passed, but processes and support were not ready. I kept acceptance open, funded process and business capacity from the approved reserve, and agreed recovery of delayed support hiring. The local team demonstrated independent operation before its manager accepted the handover.

ACCEPTANCE

What “done” meant.

Distinct checks, not a fixed sequence.

APPLICATION

The application works.

Test the tool against its requirements.

HANDOFF

The next system can use it.

Verify received records and a complete business scenario.

OPERATIONS

The local team can run it.

Confirm independent operation and the local manager’s acceptance.

ROLLOUT & CLOSURE

Prove the whole process. Then extend it.

We assembled the solution at one oilfield. Business confirmation of operating and economic benefit preceded rollout approval. Other fields needed adapted data, models, settings, integrations and procedures. Six-month final confirmation of the nonproductive-time result ran alongside remaining deployments, ending before the final month for closure and audit—all within the approved three years.

Outcome

Delivery completed. Operating results confirmed.

  • Completed scope, procedures, handover and closure within the approved $32M budget and three-year timetable.
  • Digital-twin coverage grew from about 30% to over 90% of all wells in the fields within program scope.
  • 27% lower nonproductive time in well construction, confirmed by the business using comparable wells. Comparisons accounted for well type, design, depth, geology and drilling complexity. This is not total construction time or production-well downtime.
  • The business confirmed average annual hydrocarbon production uplift of about 1.5% across fields in scope, reflecting combined organizational and IT changes.

Responsibility

My role and the scope of this case.

I led the PMs, cross-project decisions and acceptance. Engineers owned detailed design and implementation; business owners owned operating processes. Results reflect their combined work. The $32M total program budget is separate from the wider $160M+ annual portfolio and its $17M first-year effects. Thirty-five sites does not mean 35 oilfields.

Hiring for similar responsibilities?

Discuss a role

A conversation about the work

Let’s talk about
the work ahead.

If you’re hiring a leader for complex programs, portfolios or products, I’d welcome a conversation.

Discuss a role

Based in Tampa, FL

Program & portfolio leadership
Product & AI leadership

U.S. work authorization
No sponsorship required

One-page profile (PDF) Connect on LinkedIn (opens in a new tab)